EPCM (Engineering, Procurement, Construction, Management)
Main Objectives:
- services in evaluating options of technologies including audit and feasibility study and expediency;
- identification of target customers and supplier;
- comparative analysis of competiveness;
- evaluation of power efficiency;
- basic and technical design, development of the feasibility projects, work related documentation, production design work, crane production design work, expert opinions;
- performing duties and functions of the General Contractor;
- production and delivery services;
- installation and construction work performance;
- balancing and commissioning;
- registration of documentation on object.
MAJOR COMPLETED PROJECTS
2014 – 2016 Construction of electric boiler station No.1 (North) of the Boguchansky Aluminium Factory in the Boguchany region, Krasnoyarsk Territory
Client: ZAO“Boguchansky Aluminium Factory”
Period of execution: August 2013 – December 2014; April 2015 – present time
Scope of work:
- Development of Work Performance Project, preparatory work;
- Earth work with excavation of foundation pits.
- The equipment and building foundation works.
- Installation of the prefabricated reinforced concrete structures.
- Manufacturing and installation of the construction metal structures.
- Setting up the building envelope and the roofing.
2016 Running repairs of the process equipment, piping systems, structures and transfer mechanisms
Client: OAO Ilim Group Ust-Ilimsk office
Period of execution: July 2016
Scope of work:
- Repair of the I.D.fan of Soda Recovery Boiler SRB-2
- Replacement of the hot water pipeline at the line of pumps
2015 – 2016 Modernization of a boiler unit E-75-40K, station No. 16
Client: OAO Ilim Group Ust-Ilimsk office
Period of execution: 2015 – 2016
Scope of work:
Modernization of a boiler unit E-75-40K, station No. 16, with the performance increased up to 75 tph (without combustion of the backup fuel) using the fluidized bed combustion technology:
- Dismantling of the boiler unit of E-75-40K.
- Preparatory works:
- Taking the utility networks out of the constructions footprint;
- Works on the rooftop (the dismantling of the coverage items and roof slabs, reinforcing of the support pillars, installation of the temporary roof slabs, the roof maintenance, waterproofing application).
- Acting as the General Designer.
- Acting as the General Supplier.
- Acting as the General Contractor.
- Dismantling of the boiler unit of E-75-40K.
- Basic engineering, technical project, working documentation, Work Performance Project, Method Statements for crane operation, examination, approval, commissioning readiness and assurance.
- Manufacturing and delivery of the boiler E-75-3,9-440 DFT and the boiler accessories.
- Delivery of all equipment (including imported, with customs clearance) and materials.
- Organization and the full range of construction and installation work in all sections of the project:
- Foundations;
- Installation of the boiler carcass;
- Installation of the HYBEX grate;
- Installation of the boiler components (platforms, drums, screens, panels, steam superheaters, air super heaters, primary and secondary economizer); pipelines within the boilers etc);
- Installation of the boiler piping;
- Gas ducts and air ducts;
- Installation of the auxiliary boiler equipment (soot blowing equipment and exhaust fans, conveyors, air heaters etc);
- Installation and setup of Instrumentation and Controls and Automatic Process Control System;
- Installation and setup of the cable systems and illumination light;
- Installation and setup of the insulation and the refractory brickwork;
- Startup and commissioning, operational tuning and putting the boiler unit into operation.
2014 – 2015 Reconstruction of the boiler station No.2 in the city of Yelizovo (Ryabikova Str., 59a) with the construction of an extra gas power block of a carcass type with the block arrangement of the equipment
Client:OAO Kamchatskenergo
Period of execution:2014-2015
Scope of work:
- Preparatory work.
- The equipment and building foundation works.
- Installation of the prefabricated reinforced concrete structures.
- Manufacturing and installation of the construction metal structures.
- Setting up the building envelope and the roofing.
- Installation of the utility networks.
- Supply of equipment and materials.
2013 Reconstruction of the turbinal house of the boiler-turbine shop of the Thermal Power Plant 3 with the installation of two turbines R-32-8,8/0,65 station No.1 and R-27-8,8/1,35 station No. 4
Client:OAO Ilim Group Bratsk office
Period of execution:2012 – 2013
Scope of work:
- Development of Work Performance Project, preparatory work
- Manufacturing and supply of support and suspension system of pipelines.
- Manufacturing and supply of piping joints
- Installation of pipelines from boilers to turbines.
- Installation of the turbines’ piping.
- Installation the steam pipelines from the 9,0 MPa soda-regenerating boilers SRK-3000 to the turbines
2012 Construction of boiler SRB-3000 №14 Thermal power plant OAO “ILIM” Group”” Bratsk city.
Client: OAO “ILIM” Group”” Bratsk office.
Period of execution: 2011-2012
Scope of work:
- Development of project for implementation of construction operations, preparatory work.
- Installation of piping and boiler binding fittings and connection to utilities, weight is 100 tons.
- Manufacturing and delivery of the hanger support system of pipelines.
- Installation of piping from SRB-3000 to turbines №1 и №4.
2011 Modernization of boiler Barnaul Boiler Plant -75-39 №8,9 Thermal power plant ОАО «Selengynsky Pulp and Paper Mill»
Client: ОАО «Selengynsky Pulp and Paper Mill»
Period of execution: April – February 2011
Scope of work:
- Replacement of superheater.
- Replacement of feedwater economizer.
- Replacement of air preheater.
- Replacement of desuperheater.
- Replacement of water wall tube furnance.
- Replacement of downcomer and water wall tubes.
- Repair of rotating boiler machinery.
2010 Modernization of boiler Barnaul Boiler Plant -75-39 №6 thermal power plant ОАО «Selengynsky Pulp and Paper Mill»
Client: ОАО «Selengynsky Pulp and Paper Mill»
Period of execution: August – November 2010
Scope of work:
- Development of project for implementation of construction operations, preparatory work.
- Replacement of superheater.
- Replacement of ceiling superheater.
- Replacement of desuperheater.
- Replacement of front curtainwall.
- Replacement of downcomer and water wall tubes.
- Repair of boiler frame.
2010 Reconstruction of the soda recovery boiler unit SRB-1750, №11 Thermal Power Station
Client:OAO “ILIM” Group”” Bratsk office.
The project participants:ОАО «Belenergoremnaladka» (Republic of Belarus, Minsk city)
Period of execution: May 12 to May 21, 2010 (10 days)
The scope of work:
- Development of project for implementation of construction operations, preparatory work.
- Replacement of the superheater.
- Replacement of separation drum.
2009-2010 Construction of the boiler unit Е-90-3,9-440 ДФТ №15
Client: OAO “ILIM” Group”” Bratsk office.
The project participants:ООО «Energotehnomash», Metso Power OY (Finland), ООО «InterKon» Belgorod city
Period of execution:
Start of design works – October 2007
Foundations – May-August 2008
Temporary lack of funding
Main complex of construction and installation works May 2009 – February 2010
The first kindling – February 2010
The final phase of work – March-September 2010
Getting a permit to operate – September 2010
Scope of work:
- Basic engineering, detail design, working documentation, production design of the crane, production design examination, reconciliations, registration in Federal Environmental, Engineering, Russian Technical Supervisory Authority.
- Manufacturing and delivery of the boiler, the weight is 740 tons.
- Delivery of all equipment (including imported, custom clearance) and materials.
- Organization of the whole complex of construction and installation works for all sections of the project.
- The total tonnage of metal and equipment is 1,300 tons.
|
||
2006 Replacement of the water economizer for the SRB-1750 No. 11,12, acting as a General contractor
Client:Thermal power station-3 ОАО « Pulp and Paper Mill » (Bratsk city, Irkutsk Oblast)
Authors of the project:«Kvaerner Power Oy» (Finland), ООО «Energomash-Vostochnaya Sibir» (Irkutsk city)
Period of execution:
Supply of equipment: October 31, 2005 – January 31, 2006
Main works: November 15, 2005 – August 31, 2006
Scope of work:
- Basic engineering.
- Detailed design with the supply of technical and installation documentation.
- Manufacturing and delivery of water economizer, the weight of the water economizer is 516 tons, construction and installation works for preparatory replacement of water economizer.
- Disassembly and assembly roofing, etc., putting the object into operation.
2005 Rebuild of the Heat recovery system for the Board Machine, Pulp Mill 1, Stage 2
Client: PM-1 of the PULP MILL (Bratsk, Irkutsk region)
Engineering company: «Metso Paper» (Finland), Engineering Department of the PULP MILL (Bratsk, Irkutsk region)
Duration: May – November 2005
Scope of work::
Manufacturing and installation of the supports – 45 t, air ducts, fans, heaters and pipelines of Ø 32-325, tonnage – 25 t.
2004-2005 Detail Engineering and construction of a boiler to burn liquid chemical wastes, with a capacity of 35 t of steam per hour, acting as a general contractor
Client: ООО «TOKEM» (Kemerovsky JSC «Chimprom», Kemerovo)
Engineering company: ООО «Energomash-Vostochnaya Sivir» (Irkutsk)
Duration: Octover 2004 – October 2005
Scope of work:
- Detail engineering for the project and preparation of relevant documentation.
- Dismantling, manufacturing and delivery of steel constructions, elements and materials for the boiler.
- Erection of the equipment, installation of a smoke stack 45 m.
- Adjustment and start-up.
2004 Erection of a boiler with a capacity of 3.2 t/h, acting as a general contractor
Client: ВЧД-9 st. Ulan-Ude, branch of the Russian Railways (Ulan-Ude)
Engineering company: JSC «Buryatpromstroyprojekt» (Ulan-Ude)
Duration: 1 March 2004 – 25 May 2004
Scope of work:
Delivery and installation of the ТПГУ -3.2-М, construction of the fuel oil pumps, preparation and connection of the utility networks, installation of a smoke stack 32 m.
2003 Engineering works and installation of a boiler house on a turn-key basis. Capacity 20 t/h, hydrogen burning concept, acting as a General contractor
Client: Boiler House109 JSC «Sayanskchimplast» (Sayansk, Irkutsk region)
Engineering company: JSC «Angarskneftechimproject» (Angarsk, Irkutsk region)
Duration:10 July 2003 – 15 April 2004
Scope of work:
- Preparationn of Specifications together with the Client, Detail Engineering for the project, Expertise of the project, delivery of equipment, pipelines, reducing stations and materials within the scope of the project.
- Installation of two БЭМ-10/1,3-210 V bolers.
- Delivery and installation of burners SG-80 (SAACKE, Germany) and boiler equipment, pipelines, process and power equipment, manufacturing and erection of a smoke stack 42 m, installation of the instruments and process control system.
- Connecting the boiler house to the internal utility networks, commissioning.